CalcSeed

Concrete Calculator

Enter the length, width and depth of your pour to estimate cubic yards, bags and cost.

=
Quick answer: with the default inputs (10 ft, 10 ft, 4 in, $150), the concrete needed is 1.23. At these inputs: 80 lb bags = 56, material cost = $185.19. Change any input to update the result.
Concrete needed
—

Next steps

What this calculator measures

This calculator turns the footprint of a pour into the three numbers you actually order: volume in cubic yards, the equivalent count of 80 lb bags, and the material cost at your local yard price. At the defaults it evaluates a 10 × 10 ft slab poured 4 inches thick and returns 1.23 cubic yards, 56 bags and $185.19. Concrete is sold by the cubic yard at the plant and by yield on the store shelf, so the two lists describe the same concrete in different packages.

The formula

V=l·w·d12·27V= rac{lcdot wcdot d}{12cdot 27}

The division by 12 converts your depth from inches to feet, and the division by 27 converts cubic feet to cubic yards, because one yard is three feet in each of three dimensions and 3 × 3 × 3 = 27. Depth is the input most often entered wrong: at these defaults, every added inch of depth is worth 8.33 cubic feet, or $46.30 at $150 per yard.

The bag count divides the same cubic footage by 0.6, the yield of one 80 lb bag of premixed concrete, then rounds up to a whole bag. A 60 lb bag yields about 0.45 cubic feet and a 40 lb bag about 0.30, so if you shop a different bag size, divide your cubic footage by that yield instead.

Worked example: the default 10 × 10 slab

Start with 10 × 10 × 4 ÷ 12 = 33.33 cubic feet of concrete. Divide by 27: 33.33 ÷ 27 = 1.235 cubic yards, which the tool reports as 1.23. For bags, 33.33 ÷ 0.6 = 55.6, rounded up to 56 bags of 80 lb mix. At the default $150 per yard, 1.235 × $150 = $185.19 of material.

Sanity-check the volume against the area: one cubic yard covers 81 sq ft at 4 inches, so a 100 sq ft slab needs just over a yard, matching the 1.235 the tool returns. If your order covers far less area than the excavation, the depth figure is wrong.

2026 concrete prices

Ready-mix concrete delivered runs $120–$200 per cubic yard in 2026, with a national average near $155, so the $150 default sits just under the middle of the market. Installed, a 4-inch slab lands around $4–$8 per square foot with labor included, because labor makes up about half the installed price.

ProductUnit2026 typical price
Ready-mix plantper cubic yard delivered$120–$200
Short-load serviceper cubic yard, small orders$180–$260 with fees
80 lb bag of premixper bag$4–$7
60 lb bag of premixper bag$3.50–$5.50
Installed 4 in slabper sq ft, labor included$4–$8

Regional variation

Concrete and labor prices swing 15–25% between low-cost and high-cost metros. On the default slab that moves the material line between roughly $155 and $230, so it is worth collecting two local per-yard quotes before committing to a large pour.

Bags or a ready-mix truck

Both outputs describe the same concrete, so compare them directly: 45 bags of 80 lb mix make one cubic yard, which means bags and ready-mix cost the same when a bag costs one forty-fifth of the yard price — about $3.33 at the $150 default. Store bags usually cost more, so the truck wins on price past roughly one yard. Below about one yard no plant will sell a partial truck without short-load fees of $50–$150, so bags are the only practical option for a small pad or post footing.

  • Under 1 yard: bags only — short-load fees exceed the concrete savings on deliveries that small
  • 1–2 yards: truck if you can place it in one session, bags if you can work in segments
  • Over 2 yards: truck — 112 or more bags of hand mixing in a single day is beyond most DIY crews
  • Structural pours such as driveways and garage floors: truck, always — segmented bag pours leave cold joints

Waste factor and ordering extra

Concrete is the one material you cannot pick up mid-pour, so add a cushion: 5–10% on a well-formed slab over flat ground, and 10–15% on uneven subgrade or irregular shapes. On the default order, 5% takes 1.235 yards to 1.296 yards ($194.44) and 10% to 1.358 yards ($203.70) — $9.26 or $18.51 of insurance on a $185 pour. The alternative is a cold joint where fresh concrete meets concrete that has already set, a structural weak point rather than a cosmetic flaw.

For bags the rounding is built in: the tool already rounds up, so 56 bags on a 55.6-bag job carries most of the waste margin for free. For truck orders, round up to the next quarter yard, because plants batch in 0.25-yard increments and charge for what they load.

Mistakes that change the volume

  • Measuring depth at the design thickness instead of averaging the excavated subgrade
  • Typing depth in feet instead of inches — the box expects 4, not 0.33
  • Forgetting thickened edges and footings, which are separate volumes — run the tool twice and add
  • Ignoring slope: a patio needs a fall away from the house, which makes depth a range rather than a number
  • Ordering exactly the calculated volume with no 5–10% cushion

The half-inch is the expensive mistake because it is the one nobody measures. On a 20 × 20 ft driveway, a slab averaging 4½ inches when you ordered for 4 inches under-orders by 0.62 cubic yards — $92.59 at $150 a yard, or 27 extra bags. Measure depth in several places and use the average, not the plan figure.

Depth of a 10 × 10 slabCubic yards80 lb bagsCost at $150/yd
2 in0.6228$92.59
3 in0.9342$138.89
4 in1.2356$185.19
6 in1.8584$277.78
8 in2.47112$370.37

What a yard buys in coverage

A cubic yard covers 81 sq ft at 4 inches, 108 sq ft at 3 inches and only 54 sq ft at 6 inches. Halving the depth doubles the coverage, which is the fastest check on the whole estimate: multiply your order of yards by the coverage for your thickness and compare it with the area you measured. Thickness guidance is straightforward — patios 4 inches, driveways 4–5 inches with thickened edges, garage floors 6 inches or more.

DIY or hire a crew

Under about two cubic yards, a DIY pour is reasonable with help: the default 56-bag slab is heavy but manageable, and a rented mixer runs $50–$75 a day. Above two yards, a truck arrives in minutes and a crew places and finishes the pour while it is workable, with labor pushing the installed price to $4–$8 per sq ft.

Finishing is the skill that decides the result. Screeding, floating and troweling all happen inside a 60–90 minute working window, and a slab that cracks or dusts from poor finishing costs more to tear out than the labor you saved. For structural pours — driveways, garage floors, anything load-bearing — hire the crew and use this calculator to check their estimate.

Frequently asked questions

How many cubic yards of concrete do I need for a 10×10 slab?

A 10 × 10 ft slab at 4 inches is 33.33 cubic feet, or 1.23 cubic yards. Order about 1.25–1.35 yards with a 5–10% cushion, or buy 56 bags of 80 lb mix.

How many 80 lb bags of concrete make a cubic yard?

About 45 bags, since each 80 lb bag yields roughly 0.6 cubic feet and a yard is 27 cubic feet. A 60 lb bag yields 0.45 cubic feet, so one yard takes about 60 of those.

How thick should a concrete slab be?

Patios and walkways are 4 inches; driveways 4–5 inches with thickened edges; garage floors 6 inches or more. Each added inch of depth on the default 10 × 10 slab costs $46.30 more at $150 per yard.

How much does a yard of concrete cost in 2026?

Ready-mix runs $120–$200 per cubic yard delivered, averaging about $155. The calculator’s $150 default sits mid-range, and short-load deliveries under a yard add $50–$150 in fees.

Should I order extra concrete?

Yes — add 5–10% on flat, well-formed work and 10–15% on uneven ground or irregular shapes. Concrete that runs out mid-pour leaves a cold joint, which is a structural weak point, not a cosmetic flaw.

Is it cheaper to buy bags or order ready-mix?

Bags and ready-mix cost the same when a bag costs about $3.33 at $150 per yard, and store bags usually cost more, so the truck wins past roughly one yard. Below a yard, bags are the only practical choice because plants charge short-load fees of $50–$150.

How many bags do I need for a 12×12 slab?

A 12 × 12 ft slab at 4 inches is 1.78 cubic yards, which is 80 bags of 80 lb mix or $266.67 at $150 per yard. At that size a truck delivery is usually cheaper and much faster.

Can I pour concrete myself?

Under about two cubic yards, yes, with a rented mixer at $50–$75 a day and at least one helper. Finishing happens inside a 60–90 minute window and is the step most DIY pours get wrong.

What does an installed concrete slab cost per square foot?

About $4–$8 per sq ft for a 4-inch slab with labor, roughly double the material-only figure. Labor makes up about half the installed price.

Does the depth go in inches or feet?

Inches. Typing 1 instead of 4 on the default slab reads 0.31 yards instead of 1.23, because the formula divides your entry by 12 assuming inches.

Method and sources

Calculation basis

Cost ranges reflect 2026 U.S. national averages for materials and labor; regional pricing varies, so use results as a planning baseline and confirm with local quotes.

Last updated: November 19, 2026
Formula & data sources
  • Concrete volume = l × w × d ÷ 12 ÷ 27 cubic yards; 80 lb bag yields ~0.6 cu ft.

Cite this page

Reference formats
APA 7CalcSeed. (2026, November 19). Concrete Calculator. https://calcseed.com/c/home/concrete-calculator/
MLA 9"Concrete Calculator." CalcSeed, 19 Nov. 2026, calcseed.com/c/home/concrete-calculator/.
ChicagoCalcSeed. "Concrete Calculator." Last modified November 19, 2026. https://calcseed.com/c/home/concrete-calculator/

Related calculators