Calculate an hourly shop rate from annual operating cost and billable hours, or solve for cost or hours. Free and instant.

## Quick answer

**Quick answer:** with the default inputs ($120,000, 1,500 h/year), the shop rate is **80 $/h**. Change any input to update the result.

## Default calculation

Values computed by this calculator at exactly the default inputs listed below.

### Inputs (defaults)

| Input | Value | Unit |
| --- | --- | --- |
| Annual cost | 120000 | $ |
| Billable hours | 1500 | h/year |

### Outputs at these defaults

| Output | Value | Unit |
| --- | --- | --- |
| Shop Rate | 80 | $/h |

## Formula

```text
Shop rate = annual cost ÷ billable hours
```

## Inputs

| Variable | Type | Unit | Default |
| --- | --- | --- | --- |
| Annual cost | number | $ | 120000 |
| Billable hours | number | h/year | 1500 |
| Shop rate | number | $/h | 80 |

## Outputs

| Result | Format |
| --- | --- |
| Shop Rate | primary |

## How it works

### What the calculator returns

Enter what the shop spends in a year and the hours it can actually bill, and you get the hourly rate that covers both. At the defaults, $120,000 of annual cost over 1,500 billable hours is **$80 per hour**. That figure is break-even before profit, and it is the number every quote has to clear.

### What belongs in annual cost

Annual cost is every dollar the shop has to spend whether or not a job is running. Wages and payroll taxes for the people, rent or mortgage on the floor space, machine payments or depreciation, power, tooling, coolant, insurance, software and the bookkeeping. Leave one out and the rate comes back low, which is how shops end up busy and broke.

Machine cost deserves its own line because it is the easiest to understate. A $60,000 VMC over seven years is $8,571 a year in depreciation alone, before you count the $4,000 rebuild at year five or the $1,200 a year in preventive maintenance. Buying the machine with a loan does not make it cheaper; it moves the cost from depreciation to interest plus principal.

| Cost line | Annual amount | Share of total |
| --- | --- | --- |
| Wages and payroll taxes, one machinist | $55,000 | 46% |
| Rent, 2,000 sq ft | $18,000 | 15% |
| Machine depreciation or payments | $20,000 | 17% |
| Power | $6,000 | 5% |
| Tooling and consumables | $12,000 | 10% |
| Insurance, accounting, admin | $4,000 | 3% |
| CAD/CAM and software | $5,000 | 4% |

Those lines total $120,000, which is the default. Note that labour is under half of it. A shop that prices as though labour is the only cost charges roughly half what it needs, and the error compounds because the same underestimate repeats on every job.

### The billable hours problem

A full-time employee is present for about 2,080 hours a year: 40 hours times 52 weeks. Subtract 10 holidays and 10 vacation days and you are at 1,920. Subtract breaks, training, maintenance, quoting, sweeping and the inevitable waiting for material and the billable figure lands near **1,500**, which is 72 percent of the theoretical maximum.

That gap is the single biggest reason shop rates look high to customers. The $120,000 has to be recovered from 1,500 hours, not 2,080. If you divide by 2,080 instead, the rate comes out at $57.69 and the shop loses $22.31 on every hour it sells. At 1,500 hours a year that shortfall is $33,462 — enough to erase a normal profit and then some.

Utilization also depends on the machine mix. A shop running one spindle can rarely exceed 1,600 billable hours on that spindle; a shop with three machines and one operator may bill 2,000 hours because the operator tends two machines at once. The hours you can sell are a property of the whole shop, not of one person.

### Worked example at the defaults

Cost $120,000 ÷ 1,500 billable hours = **$80 per hour**. A job that takes four hours on the floor therefore has to be quoted at $320 before material and before profit, assuming the four hours are all billable. In reality a four-hour job absorbs about five hours of clock time, which is the 80 percent utilization already baked into the 1,500-hour figure.

The rate is very sensitive to the denominator. Drop to 1,200 billable hours and the same cost needs $100 per hour, a 25 percent rise. Push utilization to 1,800 hours and the rate falls to $66.67, a 17 percent cut. That is why an extra machine, a second shift or a leaner setup process changes pricing more than a small cut in rent ever will.

### Adding profit on top

The $80 covers cost and nothing else. A 15 percent margin puts the price at $80 ÷ 0.85 = $94.12; a 25 percent margin gives $106.67. Note the division: margin is a share of the selling price, so dividing by one minus the margin is the correct move. Multiplying by 1.15 instead gives $92 and quietly under-recovers by $2 an hour.

Profit also has to fund things that are not in the annual cost: a machine bought from retained earnings, a slow quarter, a bad debt. Many shops run 20–30 percent margin for that reason rather than the 10 percent a textbook would suggest. On this cost base, 25 percent margin means a posted rate near $107 rather than $80.

### What moves the rate

- Billable hours: falling from 1,500 to 1,200 pushes $80 to $100 per hour
- Wages: a $10,000 raise across the shop adds about $6.67 per billable hour
- Machine count: a second spindle adds cost and, if it is busy, billable hours
- Automation: a pallet changer that adds 300 billable hours cuts the rate about 17 percent
- Floor space: $18,000 of rent is $12 per billable hour at 1,500 hours
- Tooling discipline: $3,000 of unnecessary inserts is $2 per billable hour

### Common mistakes

#### Dividing by the hours on the clock

Using 2,080 hours instead of 1,500 is the classic error and it always runs in the same direction: the rate comes out too low. If your calculated rate is well under the local market — say $58 in a market at $90 — suspect the denominator before you celebrate your efficiency.

#### Forgetting the owner&rsquo;s pay

An owner who draws $80,000 and does not put it in the annual cost is pricing the shop as though their own labour is free. The rate then looks competitive but the owner is subsidising customers. Put the draw in the wage line at a market salary, and take profit separately.

#### Three checks before you post a rate

- Confirm billable hours come from a real time log, not a guess
- Confirm the owner&rsquo;s compensation sits in the cost, not in the profit
- Confirm the margin is applied by division, not by adding a percentage

### Comparing the result to the market

A one-machine job shop with manual and 3-axis work typically posts $75–$125 per hour in 2026, five-axis and lights-out shops $150–$250, and prototyping shops with engineering attached higher still. If the calculated $80 sits at the bottom of that band, the shop is either very efficient or undercharging. The way to tell is the margin: if quotes at $80 leave nothing at year end, the cost base is missing something or the billable hours are overstated.

## FAQ

### How do I calculate a shop rate?

Divide annual cost by billable hours. At $120,000 of cost and 1,500 billable hours the break-even rate is $80 per hour, before material and profit.

### How many billable hours should I use?

About 1,500 for a one-machine shop with one operator, out of 2,080 paid hours. Holidays, vacation, maintenance and quoting take the rest. Using 2,080 understates the rate by 28 percent.

### What counts as annual cost?

Wages and payroll taxes, rent, machine depreciation or payments, power, tooling, coolant, insurance, accounting and software. On a $120,000 shop, wages are about $55,000 and machines about $20,000.

### Should the owner&rsquo;s salary be in the cost?

Yes, at a market rate for the work. Leaving it out makes the rate look competitive while the owner subsidises every job. A $80,000 draw is $53.33 per billable hour at 1,500 hours.

### How much profit should I add?

Add 20–30 percent as a margin on the break-even rate. At $80, a 25 percent margin gives $106.67, calculated as 80 ÷ 0.75 rather than 80 × 1.25.

### What is a typical machine shop rate in 2026?

About $75–$125 per hour for a one-machine job shop doing 3-axis work, $150–$250 for five-axis and lights-out operations. Rates below $60 usually mean the cost base is incomplete.

### Why is my shop busy but not profitable?

The rate is probably below break-even. At $80 per hour and 1,500 hours the shop collects $120,000, which exactly covers cost and leaves nothing. Any quote under $80 loses money on that hour.

### Does running a second shift lower the rate?

Yes, if the added hours are billable. Adding 300 billable hours drops the rate from $80 to $66.67 on the same cost base, because the fixed cost is spread wider.

### How do I price a job from the shop rate?

Multiply the rate by the hours the job consumes, then add material and outside services. Four hours at $80 is $320; with a 25 percent margin the shop rate becomes $106.67 and the job price $426.67.

## Method and sources

Methodology: Formulas follow standard machining practice consistent with Machinery’s Handbook conventions; always verify final settings against the tooling supplier’s data.

Last updated: 2026-11-17.
- Shop rate = annual cost ÷ annual billable hours.