slug: rebar-calculator
title: "Rebar Calculator"
category: home
updated: 2026-11-17
canonical: https://calcseed.com/c/home/rebar-calculator/
html: /c/home/rebar-calculator/
---

# Rebar Calculator

Estimate the number of rebar bars and total length for a slab grid at a given spacing.

## Quick answer

**Quick answer:** with the default inputs (20 ft, 20 ft, 12 in), the total length is **840**. At these inputs: total bars = **42**. Change any input to update the result.

## Default calculation

Values computed by this calculator at exactly the default inputs listed below.

### Inputs (defaults)

| Input | Value | Unit |
| --- | --- | --- |
| Slab length | 20 | ft |
| Slab width | 20 | ft |
| Bar spacing | 12 | in |

### Outputs at these defaults

| Output | Value | Unit |
| --- | --- | --- |
| Total length | 840 |  |
| Total bars | 42 |  |

## Formula

```text
total length = bars_x_ × width + bars_y_ × length
```

## Inputs

| Variable | Type | Unit | Default |
| --- | --- | --- | --- |
| Slab length | number | ft | 20 |
| Slab width | number | ft | 20 |
| Bar spacing | number | in | 12 |

## Outputs

| Result | Format |
| --- | --- |
| Total length | primary |
| Total bars | number |
| Total length | unit |

## How it works

### What this calculator does

A concrete slab is reinforced with a grid of steel bars running in two perpendicular directions, and the grid determines both how many bars to buy and how much steel goes into the pour. This calculator takes the slab dimensions and the bar spacing, then returns the bar count in both directions and the total linear footage of rebar. For the default 20 × 20 ft slab at 12 inch spacing it returns **42 bars** totaling **840 ft** of steel.

### How the rebar grid formula works

Counting works the same in each direction: divide the opposite dimension by the spacing and add one, because a grid has a bar at both edges. A 20 ft slab at 12 inch spacing holds 20 ÷ 1 + 1 = 21 bars per direction, so 21 bars run the 20 ft width and 21 run the 20 ft length. Total length is 21 × 20 + 21 × 20 = 840 ft. The bars in one direction lie on top of, or below, the bars in the other, with tie wire locking the intersections.

Spacing controls the count more than anything else. Residential slabs commonly use 12 to 18 inch grids; driveways and slabs carrying vehicles drop to 12 inches, while light patios sometimes stretch to 24 inches. Code and engineer drawings always specify the spacing, so match the drawing before ordering.

#### Grid count for a 20 &times; 20 ft slab

| Spacing | Bars per direction | Total bars | Total length |
| --- | --- | --- | --- |
| 24 in | 11 | 22 | 440 ft |
| 18 in | 14 | 28 | 560 ft |
| 12 in | 21 | 42 | 840 ft |
| 6 in | 41 | 82 | 1,640 ft |

Halving the spacing from 12 to 6 inches doubles the steel from 840 ft to 1,640 ft — and doubles material cost with it. That is one reason spacing is set by load requirements rather than by feel: tighter grids help crack control, but you pay for every extra bar.

### Rebar sizes: #3 through #8

Bar numbers describe the diameter in eighths of an inch: a #4 bar is 4/8 in, or half an inch. Weight per foot scales with the square of the diameter, so stepping from #4 to #5 adds 56% more steel per foot. Residential slabs almost always take #4; #3 appears on thin decorative slabs, and #5 and up belong in footings, walls and engineered work.

| Bar size | Diameter | Weight per ft | Typical use |
| --- | --- | --- | --- |
| #3 | 3/8 in | 0.38 lb | patios, walkways, light slabs |
| #4 | 1/2 in | 0.67 lb | residential slabs, driveways |
| #5 | 5/8 in | 1.04 lb | thick slabs, grade beams |
| #6 | 3/4 in | 1.50 lb | foundation walls, columns |
| #8 | 1 in | 2.67 lb | heavy footings, structural work |

At the default 840 ft of #4 bar, steel weight comes to 840 × 0.67 ≈ 563 lb. That figure matters for delivery: a typical pickup handles about 800–1,000 lb of rebar, so one truck trip covers this slab, but a 1,640 ft order would need two.

### Worked example: the 20 &times; 20 ft patio slab

Run the defaults: bars per direction = floor(20 ÷ 1) + 1 = 21, total bars = 42, total length = 42 bars over 20 ft runs = 840 ft. Bars are sold in 20 ft sticks, so 840 ÷ 20 = exactly 42 sticks — but that leaves zero margin for laps, edge clearance and offcuts. Ordering 46–48 sticks (about 10% extra) is standard practice, and a few dollars of spare bar beats a mid-pour shortage.

### What moves the number

- Spacing: each halving doubles bar count and length, from 440 ft at 24 in to 1,640 ft at 6 in on this slab
- Bar size: heavier #5 bar on the same grid weighs 56% more per foot than #4
- Overlap splices: where bars butt, lap splices of 12–18 in add length the grid math ignores
- Edge clearance: bars sit 2–3 in from slab edges, trimming each run slightly
- Chairs and support: bar chairs every 2–3 ft hold the grid at mid-slab height

### Placement details that matter more than count

Rebar does nothing if it lies on the ground. Bars must sit in the middle third of the slab — for a 4 in slab, about 2 in from the surface — held on chairs so concrete flows beneath them. Fiberglass or plastic chairs every 2–3 ft along each bar are cheap insurance. Where two runs meet the perimeter, keep bars 2–3 in from the form boards so the steel is fully encased; exposed rebar rusts and spalls concrete from the edge inward.

#### Common mistakes that cost real money

- Ordering exactly the calculated footage with no lap allowance, then splicing short
- Using #3 bar on a vehicle slab because it was cheaper, then watching cracks widen within two winters
- Tying the grid flat on plastic sheeting without chairs, leaving the steel at the bottom of the pour
- Spacing bars 24 in where the drawing says 12 in, halving crack control for a modest saving

### What rebar actually costs in 2026

Rebar prices track steel markets, but a working range helps: #4 bar runs roughly $0.55–$0.85 per foot in 20 ft sticks, so the default slab&rsquo;s 840 ft costs about $460–$715 in steel. Adding chairs, tie wire and 10% spare bar brings the steel package near $550–$850. That is a fraction of a concrete bill for the same slab — roughly 4 cubic yards of delivered concrete runs $650–$900 — which is why skimping on steel saves so little and risks so much.

### When a slab needs more than a flat grid

Grid spacing and bar size come from the slab&rsquo;s job. A 4 in patio on stable soil takes #4 at 12–18 in. A 5–6 in driveway over clay takes #4 at 12 in with the grid at mid-depth. Slabs bridging expansive soils, spanning grade beams or carrying concentrated loads move into engineered territory with #5 and #6 bars, thicker sections and added mat layers. If your project carries a building, a retaining structure or vehicle loads on poor soil, use this calculator for the material count but get the spacing and bar size from an engineer&rsquo;s drawing rather than from rules of thumb.

## FAQ

### How much rebar do I need for a 20 by 20 slab?

At 12 inch spacing the grid holds 21 bars per direction, 42 bars total, running 840 linear feet. In 20 ft sticks that is 42 sticks, with 46–48 ordered in practice to cover laps and offcuts.

### What spacing should rebar use?

Twelve to eighteen inches is common for residential slabs; driveways and vehicle slabs sit at 12 in, while light patios sometimes stretch to 24 in. Match any engineer drawing exactly.

### What size rebar for a 4 inch concrete slab?

#4 (half-inch) bar is the standard for residential slabs, patios and driveways. #3 works for thin decorative slabs; footings and structural slabs move to #5 and larger.

### How do I calculate rebar for a slab?

Divide each dimension by the spacing, add one bar per direction, then multiply bars by their run length and add both directions. A 20 ft slab at 12 in spacing gives 21 bars per way and 840 ft total on a 20 × 20 grid.

### How much does rebar cost for a slab?

#4 bar runs about $0.55–$0.85 per foot, so 840 ft costs roughly $460–$715 before chairs, wire and spare bar. The full steel package on this slab lands near $550–$850.

### What does the # mean on rebar?

The number is the diameter in eighths of an inch: #4 is 4/8 in (0.5 in), #5 is 5/8 in, #8 is a full inch. Weight per foot rises with the square of the diameter, so #8 at 2.67 lb/ft weighs four times #4.

### Does rebar go on the ground or on chairs?

On chairs. Bars must sit mid-slab — about 2 in down in a 4 in slab — so concrete bonds beneath them. Rebar flat on the ground adds almost no strength.

### How many loops of bar fit in one direction?

The formula is dimension ÷ spacing + 1 per direction. At 18 in spacing on a 20 ft run that is floor(20 ÷ 1.5) + 1 = 14 bars per direction, 28 total, and 560 ft of steel.

### Can I use mesh instead of rebar in a slab?

Welded wire mesh works for light patios and walkways and must also be chair-supported. Vehicle slabs and structural work generally specify rebar for its tighter, adjustable grid and better crack control.

## Method and sources

Methodology: Cost ranges reflect 2026 U.S. national averages for materials and labor; regional pricing varies, so use results as a planning baseline and confirm with local quotes.

Last updated: 2026-11-17.
- Rebar grid count = dimension ÷ spacing + 1 in each direction.