# Footing Calculator

Estimate the concrete volume for a continuous wall footing from its length, width and depth.

## Quick answer

**Quick answer:** with the default inputs (50 ft, 16 in, 8 in), the concrete volume is **44.44**. Change any input to update the result.

## Default calculation

Values computed by this calculator at exactly the default inputs listed below.

### Inputs (defaults)

| Input | Value | Unit |
| --- | --- | --- |
| Footing length | 50 | ft |
| Footing width | 16 | in |
| Footing depth | 8 | in |

### Outputs at these defaults

| Output | Value | Unit |
| --- | --- | --- |
| Concrete volume | 44.4444 |  |

## Formula

```text
volume = length × width ÷ 12 × depth ÷ 12
```

## Inputs

| Variable | Type | Unit | Default |
| --- | --- | --- | --- |
| Footing length | number | ft | 50 |
| Footing width | number | in | 16 |
| Footing depth | number | in | 8 |

## Outputs

| Result | Format |
| --- | --- |
| Concrete volume | primary |
| Concrete volume | unit |

## How it works

### What the output measures

The calculator returns concrete volume in cubic feet for one continuous footing run. At the defaults a **50 ft** long, **16 in** wide, **8 in** deep footing gives **44.44 cu ft**. That is the pour volume only: it does not include a slab, a pier, or the extra you lose to an uneven trench bottom. Convert to cubic yards before you call a ready-mix plant, because that is the unit they sell.

### The volume formula

Length is already in feet. Width and depth arrive in inches, which is how footings are specified in plans and how forms are actually built, so each is divided by 12 before multiplying. Leaving one dimension in inches inflates the answer twelvefold, which is the single most common arithmetic error on this calculation.

The formula assumes a rectangular section with vertical sides and a flat bottom. A footing poured against sloped trench walls, which is legal in some soils, uses more concrete than the nominal rectangle because the trench is wider at the top. If the excavation bellies out, add 10–15% rather than trusting the theoretical figure.

### Worked example at the defaults

Take 50 ft of 16 in by 8 in footing. The width in feet is 16 ÷ 12 = 1.333 ft and the depth is 8 ÷ 12 = 0.667 ft. Multiply through: 50 × 1.333 × 0.667 = **44.44 cu ft**.

Divide by 27 to get cubic yards: 44.44 ÷ 27 = **1.65 cu yd**. A ready-mix truck typically has a 3 cu yd minimum with a short-load fee below that, so this pour either pays a surcharge or gets rounded up. In bags, an 80 lb bag yields about 0.6 cu ft, so 44.44 ÷ 0.6 = **74 bags**. A 60 lb bag yields 0.45 cu ft and needs 99 bags, which is why footing pours are usually ordered from a plant.

### Concrete per 10 feet of footing

| Footing size | Volume per 10 ft | 80 lb bags | Typical use |
| --- | --- | --- | --- |
| 12 × 6 in | 5.00 cu ft | 8 | garden wall, low fence |
| 16 × 8 in | 8.89 cu ft | 15 | single-story stud wall |
| 20 × 10 in | 13.89 cu ft | 23 | two-story or masonry wall |
| 24 × 12 in | 20.00 cu ft | 33 | heavy veneer, retaining load |

Read the table as a rate, not a limit. The 16 × 8 row is exactly the default section, so 50 ft of it is five times 8.89, which returns the 44.44 cu ft above. Using the row rate is faster than re-running the formula for every wall segment, and it makes it obvious when a 12 in section would carry the same load for 40% less concrete.

### Continuous footing versus isolated pad

A continuous or strip footing is what this tool models: a long prism under a wall, carrying load along its whole length. An isolated footing, sometimes called a pad or pier footing, is a short block under a single post, and it is calculated one pad at a time then multiplied by the count. The two are not interchangeable. A deck or porch post needs a pad sized for its point load, while a foundation wall needs a continuous run so the load never lands on an unreinforced span of soil.

The practical difference shows up in the numbers. A 2 ft square, 12 in deep pad is 4 cu ft, so six deck posts need 24 cu ft, roughly half the concrete of the 50 ft strip wall and spread across six separate holes. Mixing the two methods produces the classic error of pricing a foundation as though it were a set of pads, which under-orders concrete by a wide margin on any wall longer than about 20 ft.

### What moves the volume

- Width is the biggest lever: going from 16 in to 20 in adds 25% to the pour at the same depth.
- Depth set by the frost line dominates in cold climates, where 36–48 in is common against 12 in in the South.
- Wall length is linear, so a 100 ft run at the default section needs 88.89 cu ft, or 3.29 cu yd.
- Trench over-excavation adds 10–15% in sandy or rocky soil where walls cave between forming and pouring.
- A stepped footing on a slope pours in level segments, and each step adds a small overlap volume.

Frost depth is the variable people underestimate. A footing must bear below the frost line, so the same 16 in wide wall is 8 in deep in Georgia and 42 in deep in Minnesota. That is roughly 5.25 times the concrete for the same wall length, and it is the reason a foundation quote from one climate tells you nothing about another.

### Ordering and waste

Add 5–10% to the calculated volume for a formed footing and 10–15% for one poured against soil. At the defaults, 44.44 cu ft becomes about 1.75 cu yd, which conveniently clears the common 3 cu yd truck minimum only if you round to a full yard and a half.

- Order ready-mix in &frac14; yd increments and expect a short-load fee below 3 yd.
- Bag mixing suits pours under about 1 cu yd; above that the labour cost exceeds the delivery fee.
- Keep two extra bags on site for a cold joint or a low corner rather than stopping mid-pour.

### Code rules the arithmetic cannot see

Volume does not tell you whether the footing is legal. Most residential codes require the footing to be at least twice the wall thickness, bear on undisturbed soil below frost, and sit on a minimum 6 in of gravel where drainage is poor. Reinforcement is specified separately: #4 bar at 12 in on center both ways is typical, with 3 in of cover, and it does not change the concrete volume in any meaningful way.

#### When to hand the number to an engineer

Call for stamped design when the wall carries a second story of masonry, when the soil is fill or clay with a high shrink-swell rating, or when the footing steps more than 2 ft over its run. In those cases the width and depth come from bearing pressure, not from a table, and the concrete volume is the least interesting number on the drawing.

## FAQ

### How much concrete for a 50 foot footing?

At 16 in wide and 8 in deep, 44.44 cu ft, which is 1.65 cu yd or about 74 bags of 80 lb mix. Order 1.75 cu yd to cover waste and uneven trench bottom.

### How many 80 lb bags of concrete make a yard?

About 45. An 80 lb bag yields roughly 0.6 cu ft and a cubic yard is 27 cu ft, so 27 ÷ 0.6 = 45 bags.

### How deep should a footing be?

Deep enough to bear below the frost line: 12 in in mild climates, 36–48 in across the northern states, and always on undisturbed soil per the local code.

### How wide is a typical footing?

Usually twice the wall thickness. A 8 in block wall gets a 16 in footing, which is exactly the default here, and a 10 in wall steps up to 20 in.

### What is the difference between a strip footing and an isolated footing?

A strip footing is one long continuous pour under a wall. An isolated footing is a separate pad under a post, typically 2–3 ft square, calculated per pad and multiplied by the count.

### Does rebar change how much concrete I need?

Not measurably. #4 bar at 12 in on center displaces well under 1% of the volume, which disappears inside any normal waste allowance.

### How much extra concrete should I order?

Add 5–10% for formed footings and 10–15% where you pour against soil. At the default 44.44 cu ft, that means ordering 1.75 cu yd instead of 1.65.

### Can I pour a footing in bags instead of ordering a truck?

Up to about 1 cu yd, yes. The default pour needs 74 bags of 80 lb mix, which is more than most people want to mix by hand in one day.

### Why is my calculated volume lower than the concrete delivered?

Deliveries are rounded to &frac14; yd, trenches are often wider than the nominal section, and a low corner or a cold joint absorbs extra. A 10% gap between calculated and delivered is normal on a strip footing.

## Method and sources

Methodology: Cost ranges reflect 2026 U.S. national averages for materials and labor; regional pricing varies, so use results as a planning baseline and confirm with local quotes.

Last updated: 2026-11-17.
- Footing volume = length × (width/12) × (depth/12) in cubic feet.