Enter the setup time, batch size and run time per part to find the setup cost per part and the total job time.

=
Quick answer: with the default inputs (60 min, 50 parts, 2 min), the setup per part is 1.2. At these inputs: total job time = 160. Change any input to update the result.
Setup per part
—

What this calculator returns

This tool returns two numbers: the setup minutes charged to each part and the total time the job consumes. At the defaults — 60 minutes of setup, 50 parts, 2 minutes of run time each — the setup cost is 1.2 minutes per part and the job takes 160 minutes. That 1.2 is the number to add to the 2 minute run time before you apply a shop rate.

The setup amortisation formula

setup/part=SN,total=S+R·Nsetup/part = \frac{S}{N},\ total = S + R\cdot N

S is the one-time setup in minutes: fixturing, tool assembly, program proving, first-article inspection and any machine adjustment before the first good part. N is the batch size and R is the run time per part. Setup per part is S divided by N, so it halves every time the batch doubles, while the total job time is setup plus N parts at R each.

The distinction matters because only one of the two terms scales. Run time is linear in quantity, so a 100 part batch takes twice the run time of a 50 part batch. Setup does not scale at all, which is why short runs are expensive per piece and why a shop that quotes every job as if it were a 500 part order loses money on the small ones.

Worked example at the defaults

Setup takes 60 minutes, the batch is 50 parts, and each part runs 2 minutes. Setup per part = 60 ÷ 50 = 1.2 minutes. Total job time = 60 + 2 × 50 = 160 minutes, or 2.67 hours. Each part effectively consumes 3.2 minutes of machine time, not the 2 minutes the stopwatch shows during the run.

At a $75/hr burdened rate that is $4.00 per part, of which $1.50 is setup. Price the part on the 2 minute run time alone and you recover $2.50, losing $1.50 on every unit — a 37.5 percent shortfall that compounds across a 1,000 part annual order into $1,500 of unrecovered cost.

Setup per part by batch size

Batch sizeSetup per part, 60 min setupEffective minutes per partShare of time that is setup
160.0 min62.0 min96.8%
512.0 min14.0 min85.7%
106.0 min8.0 min75.0%
252.4 min4.4 min54.5%
501.2 min3.2 min37.5%
1000.6 min2.6 min23.1%
5000.12 min2.12 min5.7%

The last column is the honest measure of how much a small batch hurts. At 10 parts, three quarters of the machine time is setup; at 500 parts it is under 6 percent. There is no formula fix for that, only a decision: charge for the setup explicitly, raise the quantity, or cut the setup with quick-change tooling.

The break-even batch

Set setup per part equal to run time per part and you get the batch at which both contribute equally: N = S ÷ R. With 60 minutes of setup and 2 minutes of run, that is 30 parts. Below 30, setup dominates and every extra part saves more than it costs in run time; above 30, run time dominates and the only lever left is cycle time. A quote that assumes a batch of 20 is quoting a job where 60 percent of the time is changeover.

What moves setup per part

  • Batch size. Inversely proportional: 50 to 100 parts halves setup per part from 1.2 to 0.6 minutes.
  • Setup hours. Linear: cutting a 60 minute setup to 30 halves the charge at any batch, from 1.2 to 0.6 at 50 parts.
  • Run time. Does not affect setup per part at all, though it changes which term dominates: at 10 minutes per part, setup is under 11 percent even at 50 pieces.
  • Repeat batches. A second run of the same part skips program proving and often half the fixturing, so the second 50 piece batch might carry 20 minutes rather than 60.
  • First-article inspection. Usually 10–20 minutes of the total and it cannot be skipped on a new program.

Mistakes in setup quoting

Amortising setup over the annual quantity

Quoting 1,000 parts a year but delivering in four batches of 250 means the setup is paid four times. If each setup is 60 minutes, the real charge is 240 minutes over 1,000 parts, or 0.24 minutes per part, while the invoice only covers 60. Split the annual volume into the batches you will actually run before dividing.

Counting only the fixture change

The 60 minutes in the default is not 60 minutes of bolting. It is typically 15 minutes of teardown and clean, 20 of fixture and tool build, 15 of program load and dry run, and 10 of first-article check. Miss the last two and the first part is discovered bad after the batch has run, which adds a second setup nobody quoted.

Assuming setup is free on a repeat order

A repeat still needs the fixture found, the tools loaded, the program proven at the current revision and the first part checked. That is rarely under 15 minutes and often 25 on a machine that has run 40 other jobs since. Budget half the original setup for a repeat rather than zero.

Cutting setup instead of raising the batch

Sixty minutes of setup on a 10 part batch is 6 minutes per part, more than three times the run time. Halving setup to 30 minutes saves 3 minutes per part on that batch; doubling the batch to 20 saves the same 3 minutes without any capital spend. Do the arithmetic before buying quick-change tooling: preset toolholders pay back fast on jobs that repeat weekly, and almost never on one-off work where the setup is dominated by fixturing and program proving instead.

Frequently asked questions

How do I calculate setup time per part?

Divide total setup minutes by batch size. With 60 minutes of setup over 50 parts, each part carries 1.2 minutes, so the effective time per part is 3.2 minutes once the 2 minute run is added.

Why do larger batches cost less per part?

Setup is fixed, so it spreads thinner. At 60 minutes of setup, 10 parts carry 6 minutes each while 100 parts carry 0.6, a tenfold difference on the same job.

What is included in setup time?

Teardown and cleaning, fixture build, tool assembly, program load and dry run, and first-article inspection. On a 60 minute setup expect about 15, 20, 15 and 10 minutes respectively.

At what batch size does setup stop dominating?

When setup per part falls below run time per part, at N = S ÷ R. For 60 minutes of setup and 2 minutes of run that is 30 parts; below that, setup is the majority of the time.

How much does 60 minutes of setup cost at $75/hr?

$75 in total, or $1.50 per part on a 50 piece batch. On a 10 piece batch the same setup is $7.50 per part.

Can I ignore setup on a repeat order?

No. A repeat still needs fixture retrieval, tool loading, a program check and a first-article inspection, typically 15–25 minutes. Budget half the original setup, not zero.

How much does halving setup time save?

It halves the setup charge at any batch: 1.2 to 0.6 minutes per part at 50 pieces, or 6 to 3 minutes at 10 pieces. The saving per part scales with 1 ÷ N.

Is it cheaper to run 500 parts in one batch or five batches of 100?

One batch, if you can store them. Five batches pay five setups: 300 minutes instead of 60, which is 0.6 minutes per part instead of 0.12 on 500 pieces.

What happens to total job time as batch size grows?

It rises linearly with run time and only once with setup. At the defaults, 50 parts take 160 minutes and 100 parts take 260, a 62.5 percent increase for double the output.

Method and sources

Calculation basis

Formulas follow standard machining practice consistent with Machinery’s Handbook conventions; always verify final settings against the tooling supplier’s data.

Last updated: November 18, 2026
Formula & data sources
  • Setup per part = setup time / batch size; total job time = setup + (run time per part × batch size).

Cite this page

Reference formats
APA 7CalcSeed. (2026, November 18). Setup Time Calculator. https://calcseed.com/c/machining/setup-time-calculator/
MLA 9"Setup Time Calculator." CalcSeed, 18 Nov. 2026, calcseed.com/c/machining/setup-time-calculator/.
ChicagoCalcSeed. "Setup Time Calculator." Last modified November 18, 2026. https://calcseed.com/c/machining/setup-time-calculator/

Related calculators

More Machining calculators